Fresno County battery storage rules
Projects go through general utility, energy or use-permit rules.
- Key rules
- The Zoning Ordinance (Feb 2024 edition) contains no 'battery' or 'energy storage' text. How standalone BESS are classified needs a call to the planning desk.
- Pending action
- None found.
- Projects
- Opt-in: Darden Clean Energy (Intersect Power, 1,150 MW solar, 1,150 MW/4,600 MWh), approved by the CEC June 11, 2025; under construction. CAISO queue: 26 active storage entries (4,566 MW), incl. Apache Storage, Ciervo Mountain Hybrid, Heartland 1; 3 completed.
- Sources
A brief on Fresno County
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.
Research from public records, not legal advice. How this table is built.