El Dorado County battery storage rules
Projects go through general utility, energy or use-permit rules.
- Key rules
- Title 130 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Conditional Use Permit: Stella Battery Storage (CUP22-0010) cleared the Zoning Administrator June 5, 2024.
- Pending action
- None found in CEQAnet or news searches.
- Projects
- Stella (CUP22-0010) and Fuji (CUP22-0011) battery storage, 5 MW/20 MWh each. Fuji went to the Planning Commission July 2025; outcome not checked. CAISO queue: no storage entries.