Sacramento County battery storage rules

No battery-specific rulesChecked Nov 15, 2026

Projects go through general utility, energy or use-permit rules.

Key rules
Zoning Code has no energy storage provisions (GoCodebook copy, June 2026 edition). A shopping-center BESS enclosure went through a Special Development Permit and design review (AutoZone, Dec 2025).
Pending action
None found in CEQAnet or news searches.
Projects
Dry Creek Energy Storage (30.1-acre BESS): state incidental take permit NOD Apr 14, 2026. SMUD started an EIR for its Twin Cities Solar and BESS May 27, 2026. Most projects sit in SMUD territory, outside the CAISO queue. CAISO queue: 1 active storage entry (59 MW), incl. Prospect Energy Storage.
Sources

A brief on Sacramento County

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.

Research from public records, not legal advice. How this table is built.