Inyo County battery storage rules

No battery-specific rulesChecked Nov 15, 2026

Projects go through general utility, energy or use-permit rules.

Key rules
Title 18 (Zoning) and Title 21 (Renewable Energy Ordinance, 2010) have no energy storage provisions (GoCodebook copy, Oct 2026 edition). Title 21 covers solar, wind and transmission permits.
Pending action
ZTA 2026-01, which rewrites the renewable energy design standards in Sec. 21.20.020, went to the Planning Commission Sept 23, 2026; Board action not checked.
Projects
No BESS projects in CEQAnet since 2023. CAISO queue: 2 active storage entries (765 MW), incl. Calvada Springs Solar, Sunbaked Solar.