Colusa County battery storage rules
Projects go through general utility, energy or use-permit rules.
- Key rules
- Chapter 44 (Zoning Code) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Saloon BESS got a Major Use Permit and franchise agreement (PD-25-6).
- Pending action
- None found in CEQAnet or news searches.
- Projects
- Saloon BESS (up to 150 MW, near PG&E's Cortina substation, PD-25-6) approved Nov 18, 2025. Janus Solar and Battery Storage use permit approved Feb 25, 2025. CAISO queue: 2 active storage entries (230 MW), incl. Janus, Saloon Energy Storage.
- Sources
A brief on Colusa County
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.